Tesla Semi manufacturing facility to get large quantities of concrete, replace exhibits


Tesla has been constructing a devoted Semi plant at its Gigafactory Nevada this yr, and a current development replace exhibits preparations for an enormous quantity of concrete but to be laid.

In an replace this week from Zanegler, a Giga Nevada observer and self-proclaimed Tesla Semi advocate, footage from the location exhibits tons of current progress, together with motion photographs of truss rods going up on the now-many metal beams on the web site, and the assorted footings that may reportedly make the most of an enormous quantity of concrete.

Zanegler calls the location a “concrete jungle,” saying that every of the bigger footings highlighted within the video will use 55 yards of concrete, whereas the footings collectively will use 20,000 yards whole. Throughout everything of the undertaking, he says, a million yards of concrete will probably be laid upon completion.

As some have identified, it’s not totally clear if he means cubic yards of concrete, nevertheless it appears fairly clear that the ability will make the most of a considerable quantity of the fabric it doesn’t matter what.

Together with picturing the way forward for concrete on the web site, the video options a couple of photographs of what Zanegler calls a BZI Telehandler because it strikes horizontal truss rods onto the vertical metal beams. The metal beams first started arriving on the web site early final month, and there’s already been a major quantity of progress made on the upcoming facility since then.

In a follow-up submit, Zanegler additionally shared a close-up photograph of a concrete truck getting ready to begin pouring into one of many footings, which might be seen beneath beneath a few stills from the video.

Credit score: Zanegler | YouTube

Credit score: Zanegler | YouTube

Credit score: Zanegler | X

RELATED:

Tesla Semi fleet real-world observations shared by PepsiCo

Tesla first broke floor on the Giga Nevada Semi enlargement in January, and the corporate is aiming to start manufacturing within the second half of 2025. Preliminary buyer deliveries are anticipated for early 2026, although Tesla has already delivered its early models to prospects together with PepsiCo, Costco, Martin Brower, and Walmart, amongst others.

Moreover, Tesla has been ramping up manufacturing of the Semi at Giga Nevada’s preliminary manufacturing facility, with not less than 50 models not too long ago being noticed on web site.

Earlier this month, Tesla Semi program Senior Supervisor Dan Priestley visited the upcoming Semi manufacturing facility development web site, happening to share a photograph of some Semi models on the facility. Tesla has additionally been teasing plans for the Semi in Europe, as the corporate not too long ago displayed one unit on the IAA conference in Munich, Germany.

You’ll be able to watch the total Semi manufacturing facility development replace as posted on Zanegler’s YouTube channel on Saturday beneath.

What are your ideas? Let me know at [email protected], discover me on X at @zacharyvisconti, or ship us ideas at [email protected].